Petrochemical Facility Substation Commissioning
Scope of Work
NETA ATS commissioning of a new 13.8 kV substation including medium-voltage switchgear, power transformers, protective relays, and low-voltage distribution equipment prior to energization.
Outcome
All equipment verified to NETA ATS specifications. Three wiring discrepancies and one relay mis-setting identified and corrected before energization. Full commissioning report delivered for project closeout.